On Monday 18 May, 2020 work commenced on the long awaited play area in Calthorpe Park.

 

Whilst the installation of this exciting new facility is in progress some areas will not be accessible to the public.

 

The works will take between 9 - 12 weeks to complete and the new Play Area will be opened once the COVID 19 Government Restrictions are lifted.

 

Stay tuned for pictures as work progresses!!

 

26th June

 

18th June

 

 

W/C 15th June

W/C 8th June

 

 

Plans

 

 

 

--------------------------------------------------------------------------------------------------------------------------------------------

OLD

 

Drainage works were completed during December 2019 on the lower field in Calthorpe Park in preparation for the installation of a new play area. The Play area will consist of 3 play zones, interlinking paths, safety surfaces, accessible equipment and disabled parking.

 

At the end of 2019 a Tender to design and install play equipment was launched and bids have now been received and evaluated against the brief with a recommendation due to go through Council in February. The contract will have a completion date of July this year, just in time for the Summer holidays.

 

Calthorpe Park is currently the only park in Fleet without a children’s play area and we hope this installation will be a great benefit to the surrounding residential area.      

 

Documents

Calthorpe Park Play Area Survey - Full Council, June 2018

Calthorpe Park Play Area Graphs - RLA, December 2018